Fire Station No. 2 Parking Lot Rehabilitation

Fire Station Complete

Parking lot was in disrepair and drainage was not sufficient

 

Scope: Drainage Improvements, Full-Depth Reclamation, Paving, and Concrete Slab Construction

Contractor: White County and All About Asphalt, Inc.

Schedule: 45 Days

Budget: $192,504.75

Project Phase: Complete

Click any thumbnail image to view a slideshow

Fire Station Slab
Fire Station Grading